project management glossary

eac

 See Estimate at Completion

 See Estimated Actual at Completion

earliest feasible date

 The earliest date on which the activity could be scheduled to start based on the scheduled dates of all its predecessors, but in the absence of any resource constraints on the activity itself. This date is calculated by resource scheduling.

earliest finish

 The earliest day that the work item can finish if it starts on its earliest start and is completed in its expected time.

 In a network diagram schedule, the earliest time at which an activity can be completed.

earliest finish time

 See Earliest Finish above.

 Earliest possible time by which an activity can finish within the logical and imposed constraints of the network.