project management glossary
forced analysis
Most PM software can force schedule analysis where a project is re-analyzed
even if no new data has been entered. The feature is used for an analysis on the
project by itself after it has been analyzed with other projects in multi-
project processing (or vice versa). A leveled schedule may also be removed by
forcing schedule analysis.
forcing
The project manager uses his power to direct the solution. This is a type
of win-lose agreement where one side gets its way and the other does not.
forecast
An estimate and prediction of future conditions and events based on
information and knowledge available at the time of the forecast.
forecast at completion (fac)
Scheduled cost for a task.
forecast final cost
The sum of committed cost and estimated to complete.
The anticipated cost of a project or component when it is complete. The sum
of the committed cost to date and the estimated cost to complete.
See Cost Types and Estimate at Completion.