late start (ls)
The latest time an activity may begin without delaying the project finish
date of the network. This date is calculated as the late finish minus the
duration of the activity.
late start date (lsd)
In the critical path method, the latest possible date that an activity may
be begun without delaying a specified milestone (usually the project finish
date).