project management glossary
negative float
Negative float indicates activities must start before their predecessors
finish in order to meet a target finish date. All float is calculated when a
project has its schedule computed. Negative float occurs when the difference
between the late dates and the early dates (start or finish) of an activity are
negative. In this situation, the late dates are earlier than the early dates.
This can happen when constraints (Activity Target dates or a Project Target
Finish date) are added to a project.
Where a path in a network becomes hypercritical the activities on that
path have float of less than zero. The quantity of float then indicates the
amount of time which must be picked up in order to achieve an imposed date.
The amount of time by which the planned duration of a sequence exceeds the
time available before an imposed date. It typically occurs during project
implementation when critical activities leading to a required date are completed
late, or during planning when an initial version of the schedule does not fit
the allotted time frame. The cure is revision of logic, decrease in subsequent
durations (e.g. by "crashing") such as by increasing resources of a change in
methods. Otherwise the end date must be changed.
negative total float
Time by which the duration of an activity or path has to be reduced in
order to permit a limiting imposed date to be achieved.
