project management glossary
start event of a project
Event with succeeding, but no preceding activities (there may be
more than one start event.
start float
The amount of excess time an activity has between its Early Start and Late
Start dates.
start to finish
See Logical Relationship.
start to start
See Logical Relationship.
start to start lag
The minimum amount of time that must pass between the start of one activity
and the start of its successor(s). This may be expressed in terms of duration
or percentage.
starting activity
A starting activity has no predecessors. It does not have to wait for any
other activity to start. Many PM software packages permit multiple start
activities if needed.