target finish date
The date planned to finish work on an activity.
The user's imposed finish date for an activity or a project as a whole. A
target finish date is used if there are pre-defined commitment dates. Most PM
software will not schedule a late finish date later than the target finish date.
Your favorite PM software may alert you to negative float which occurs when a
late finish date is later than a target finish date. This is caused by the
duration of predecessors which makes it impossible to meet the target finish
date. The negative float can be eliminated by reducing the duration of
predecessors, increasing parallelism, or extending the target finish date.
target finish, activity
The user's imposed finish date for an activity. A Target Finish date is
used if there are pre-defined commitment dates.
target finish, project
A date imposed on a project as a whole, usually by the user.
target plan
The plan prioritized by critical total float taken from the current
schedule.